Factory Registration Bihar | Form-XXIII E-Filing & Licence Grant
Official Statutory Guide • Bihar OSH Rules, 2026

Application for Registration & Grant of Factory License in Bihar

Statutory Procedure, Form-XXIII E-Filing, Re-Registration & Approval Protocols Under Bihar OSH Rules, 2026

Operating a manufacturing plant in Bihar requires mandatory registration and licensing under the Occupational Safety, Health and Working Conditions Code, 2020 read with the Occupational Safety, Health and Working Conditions (Bihar) Rules, 2026 (notified in Bihar Gazette No. 699, dated July 1, 2026). These statutory rules formally supersede the historic Bihar Factories Rules, 1950, introducing a unified digital gateway, time-bound deemed approvals, and a 10-year licensing framework administered by the Directorate of Factories, Labour Resources Department, Government of Bihar.

Rule 64(10) Mandate: No occupier is legally permitted to use any industrial premises as a factory or carry out any manufacturing operations without a valid license granted by the Chief Inspector-cum-Facilitator.
Initiate Factory Registration Bihar
Fresh Establishment

New Factory Registration (Form-I & Form-XXIII)

Newly established manufacturing facilities must complete enterprise registration via Form-I (issued via Form-II) and formally apply for the grant of a factory license via Form-XXIII at least 15 days prior to commencing any manufacturing operations.

Mandatory 15-Day Prior Notice

Filing must precede plant operations, initial trial runs, or live power testing to secure statutory immunity under Section 114.

Single Window Portal Form-XXIV Granted
Rule 3(3) Mandate

Mandatory Re-Registration / Data Migration

Any establishment previously registered under the repealed Bihar Factories Rules, 1950, or related central enactments is deemed registered under the new Code. However, under Rule 3(3), the employer must update and re-register their establishment details on the state online portal within six months of the gazette publication date (by December 31, 2026) in Form-I to obtain an updated Form-II registration certificate without incurring statutory penalties.

Seamless Digitization

Existing physical factory records transition cleanly through our dedicated digitized legacy dossier protocol.

Deadline: 31 Dec 2026 Form-II Reissuance
Operational Benchmarks

Statutory Thresholds: Who Must Register in Bihar?

Every manufacturing establishment in Bihar meeting any of the following operational parameters is mandated by law to obtain registration and a factory license.

Motive Power

Units with Motive Power

Premises employing 20 or more workers on any single day of the preceding 12 calendar months with the aid of electrical or mechanical power.

Form-I & XXIII Applicable
Manual Power

Units without Motive Power

Premises employing 40 or more workers on any single day of the preceding 12 calendar months operating completely without electrical motive power.

Threshold: 40+ Workers
Rule 67 & Schedule-IV

Hazardous Operations

Any industrial unit conducting scheduled dangerous operations (foundries, electroplating, chemical synthesis, stone/silica transformation, solvent extraction, acid wash lines) requires registration irrespective of employee headcount exemptions.

Zero Workforce Exemption
Procedural Architecture

Step-by-Step Registration & Licensing Protocol

Step 1

Sanction of Building Plans (Form-XXII)

Prior to registration, civil layouts and machinery placement must be approved under Rule 64(1). Floor plans, elevations, cross-sections, ventilation profiles, and boundary GPS coordinates (Lat/Long) are filed electronically.

30-Day Deemed Clearance (Rule 64(2)(v))
Step 2

Structural Stability Certificate

The factory building must be inspected and stress-tested by a recognized Competent Person chartered under Rule 2 and Section 2(1). Under Rule 64(3), no process can begin without this certificate uploaded and accepted.

Rule 2 Empaneled Certification
Step 3

Portal Filing of Form-XXIII

The designated occupier submits Form-XXIII on the Bihar Single Window Clearance System at least 15 days prior to trial production, incorporating approved building plans, stability certifications, and workforce/HP loads.

15 Days Prior Notice Mandated
Step 4

Electronic Treasury Payment

Pay the prescribed statutory licensing fee electronically calculated against installed horsepower (HP/KW) and peak worker slabs under Schedule-III through the state cyber treasury gateway.

Schedule-III Electronic Challan
Step 5

Scrutiny & Licence Grant (Form-XXIV)

The jurisdictional Inspector-cum-Facilitator scrutinizes particulars and conducts site validation. Under Rule 64(5)(iv), if no objection is issued within 30 days, the factory license is deemed granted and auto-generates.

30-Day Deemed Grant Clause
Rule 3(10) Penalty Structure

Statutory Registration Fees & Late Delay Penalties

Base registration fees for new establishments and statutory delay penalties scale exponentially by workforce thresholds:

Compounding Penalties
Peak Employee Threshold Base Registration Fee Delay Penalty (Up to 60 Days) Delay Penalty (61 to 90 Days) Delay Penalty (91 to 180 Days) Delay Penalty (181+ Days)
10 to 49 Workers ₹500 ₹1,000 ₹5,000 ₹10,000 ₹10,000
50 to 100 Workers ₹1,000 ₹2,000 ₹10,000 ₹20,000 ₹20,000
101 to 300 Workers ₹2,000 ₹4,000 ₹20,000 ₹40,000 ₹40,000
301 to 500 Workers ₹3,000 ₹6,000 ₹30,000 ₹50,000 ₹50,000
501 to 1,000 Workers ₹4,000 ₹8,000 ₹40,000 ₹60,000 ₹60,000
1,001 to 5,000 Workers ₹5,000 ₹10,000 ₹50,000 ₹70,000 ₹70,000
5,001+ Workers ₹6,000 ₹12,000 ₹60,000 ₹80,000 ₹80,000

Statutory Reference (Rule 3(10)(2)): The registering authority may verify utility connection dates (such as initial industrial electric meter energization) to establish operational start dates and determine late fee liabilities objectively.

Documentary Verification

Mandatory Document Checklist for Form-XXIII

Ensure all required records are verified, notarized, and formatted prior to portal submission:

1

Corporate & Management Proofs

  • Permanent Account Number (PAN Card) of the business entity and Certificate of Incorporation, Partnership Deed, or LLP Agreement.
  • Formal Board Resolution or Partnership Authorization designating the legal Occupier and Factory Manager.
  • PAN Card and address proof of the Occupier and Manager (identity verification is completed electronically via portal credentials).
2

Property & Civil Clearances

  • Registered Land Title Deed, Registered Lease Deed, or BIADA Plot Allotment & Possession Certificate.
  • Formal Building Plan Approval Order issued under Form-XXII.
  • Certificate of Structural Stability in prescribed format signed by an empaneled Competent Person under Rule 64(3).
3

Environmental & Utility Approvals

  • Valid Consent to Establish (CTE) and Consent to Operate (CTO) from the Bihar State Pollution Control Board (BSPCB).
  • Fire Safety Recommendation / NOC from the Bihar Fire Services.
  • Sanctioned Industrial Power Load Letter and latest utility electricity bill.
4

Technical Manufacturing Disclosures

  • Process flow diagram showing raw material transformation, inputs, outputs, and by-products.
  • Comprehensive machinery schedule detailing equipment power ratings in Horsepower (HP) and Kilowatts (KW).
  • Material Safety Data Sheets (MSDS) for chemical and solvent inventories scheduled under Rule 69 and Schedule-II.
Post-Licensing Operations

Ten-Year Validity & Lifecycle Compliance Services

Comprehensive operational governance throughout the statutory 10-year term of your factory licence:

Ten-Year Initial License

Under Rule 64(5)(v), every factory license issued in Form-XXIV remains valid for an initial statutory tenure of 10 years.

Rule 64(5)(v) Protected

Auto-Renewal Protocol

Regulated under Rule 64(6), enabling automatic extension for up to 10 additional years upon payment of prescribed fees. Renewals past 30 days incur a 50% surcharge, rising to 100% after 90 days.

Rule 64(6) Auto-Extension

Mid-Term Modifications

Increases in installed machinery capacity (HP/KW) or peak employee thresholds require amendment processing under Form-XXV within 15 days.

Form-XXV (15-Day Limit)

Succession & Ownership Changes

Property title transfers, corporate restructuring, or takeovers require formal license transfer processing under Form-XXVI.

Form-XXVI Title Conveyance

Statutory Year-End Filings

Maintenance of unified electronic registers (Form-VIII) and electronic filing of unified annual returns under Form-IX/IXA by February 1 each calendar year.

Deadline: February 1

Operational Decommissioning

Controlled industrial cessation filing under Form-IV, certifying complete settlement of worker liabilities and hazardous material disposal.

Form-IV Closure Filing
Defect Prevention

Common Rejection Pitfalls & Remediation

Avoid procedural roadblocks by ensuring complete alignment prior to single-window submission:

Electrical Capacity Discrepancies

Declaring machinery load in Form-XXIII that contradicts the power sanction letter or connected utility readings.

Remedy: Match DISCOM Load Letter

Unsanctioned Architectural Variations

Minor layout alterations executed during civil construction without filing supplementary plan amendments under Form-XXII.

Remedy: Form-XXII Revision Filing

Non-Compliant Stability Sign-Offs

Submitting structural certificates from private engineers not formally empanelled as “Competent Persons” under Rule 2.

Remedy: Verify Rule 2 Empanelment

Incomplete Pollution Consents

Submitting an operational factory license application without securing active CTO clearances from the BSPCB.

Remedy: Concurrent BSPCB Processing
Clarifications

Frequently Asked Questions

Statutory clarifications on Bihar factory registration & Form-XXIII licensing

No. Under Rule 64(10), carrying out any manufacturing process prior to receiving the formal Form-XXIV license (or the auto-generated certificate following the 30-day deemed timeline) is illegal and subject to immediate shutdown notices under Form-XII.

Yes. While existing licenses remain recognized, Rule 3(3) requires every operational establishment to re-register on the electronic portal within six months of gazette notification (by December 31, 2026) to establish their digital profile and secure Form-II.

Under Section 90 and Rule 77, an occupier can submit an appeal to the Chief Inspector-cum-Facilitator or the State Government within 30 days of receiving the rejection order. Technical assessors from organizations like the Bihar Industries Association or the Bihar Chamber of Commerce may be engaged during the hearing.

Immediate Registration Advisory

Partner with Bihar’s Industrial Licencing Advisory

Avoid compliance delays, rejection notices, and compounding financial penalties. Our industrial licensing team handles plan drafting, single-window e-filing, and regulatory follow-ups across all BIADA industrial clusters.

Form-I & Form-XXIII zero-defect statutory drafting
Patna, Hajipur, Bihta, Begusarai, Muzaffarpur industrial hubs
Rule 2 Empaneled Structural Stability validation
Direct Filing Desk

Submit Your Factory Registration Query

Provide your factory parameters below to receive our formal statutory clearance assessment.

All inquiries are handled strictly under industrial confidentiality standards.

Action completed successfully